" "     " "
  Community Hospital - McCook, Nebraska

1301 East H Street  McCook, Nebraska 69001  308-344-2650

 
      Virtual Tour Nursery Contact Us Find Us Site Map  
       

 

 

 

 

 

 




Search our website:



 PHASE I PROJECT UPDATES

Click any of the thumbnail images below to enlarge . . . . View this entire group as a slide show by clicking on the right (next image) or left side (previous image) of the enlarged image.

Patient Wing Construction Project Begins   
October 7, 2009
Patient Wing Construction Begins   Phase 1 of a 30-month construction project at Community Hospital, begins this week with tree removal on the west side of the patient pods. The trees which were removed were too large to transplant elsewhere.

The first phase is a 14-month project constructing a new 25-bed acute patient wing housing five nursing support areas, two labor-delivery-recovery rooms, a waiting area and nursery on the west side of Community Hospital, and two isolation/hospice respite rooms and a healing garden on the southern end.

     
Trivia Facts:
December, 2009
  • The steel should arrive in early January, 2010
  • A majority of the footings have been dug and poured. It is possible to dig footings in the winter as long as the holes are not open too long, allowing the ground to freeze.
  • More than 7500 cubic yards of dirt were hauled in to prepare the project foundation. It took 440 truck loads to bring in the dirt.
December, 2009    
 
Pouring footings.
     
 
Blake Bethell, Assistant Director of Maintenance, checks the footings.
     
 
Weather interruptions.
     
January, 2010    
 
The steel has arrived for the hospital building project
     
 
Unloading the steel
     
February, 2010

 
Loose Fitted Steel Installation Close to Half Done

The framework of the patient wing continues to take shape as the steel beams are set in place. Despite cold temperatures on Tuesday, February 2, a crane moves the beams one by one over to the structure where workers set them in place. After only two weeks since the steel arrived, the loose fitted framework is close to being half done.

Next week, a second steel crew will arrive. The crew will follow behind the loose fitting crew to square, align, tighten and weld the steel already in place. The next step is to deck the first half of the building (put a steel roof on). Once the roof is decked, the north half of the building will be encapsulated in plastic and heated so a floor can be poured.

While the steel is being erected, ground sewer lines are also being installed.
 

     
  A cloudy, cold day in early morning on February 11, 2010. The steel framework for the patient wing is taking shape.
     

 
February 15

These photos were taken from the present hospital patient pod roof looking west onto the steel frame of the new patient wing.

     
  February 16

The full 300 foot length of the patient wing takes shape on the hospital hill as the steel construction continues. Workers have had several days of sunshine and warmer temperatures this week helping to keep the project on schedule.

     
  Making Their Mark

"We are the foundation of Community Hospital." Community Hospital employees, board of directors, medical staff, contract staff and Community Hospital Health Foundation board of directors were invited to sign one of two steel beams for the new patient wing, forever capturing their signatures into the steel foundation framework.

Community Hospital employees signing the beam are (from left) Nicetas Eilenberger, Darla Wilson, Karen Morthole, Sarah Wolford and Larisa O’Brien.

     
  Hanging of the Beams

Two signed beams are raised at the north end of new Community Hospital patient wing by steel workers. The horizontal beam already in place on the left was signed by medical staff and board of directors. The beam just being set was signed by Community Hospital employees. A majority of employees participated in the signing with the top, sides and underside filled with signatures. Employees had the opportunity to watch the signed beam being incorporated into the facility framework on Wednesday, February 17,2010.

     
March, 2010    
 
Preparing to pour the concrete floor on the north half of the patient wing. This half is wrapped in plastic to keep the area warm and drive the frost from the ground.
 
     
 
Pouring the concrete floor on the upper level penthouse.
     


  March 25

Pouring the concrete floor on the north side of the patient wing.

     
May, 2010    

  May 4

The contractors have been working on sheeting the outside and sealing it and also installing the hangers for all the piping, ducts and medical gasses.
     
  May 17

Outside view of Area D - this is the building that will house the new generator on the northeast side of the hospital.

     

  Bricking and roofing started on Area D
     

  Enclosing the new patient wing
     
  May 25

Fireproofing being installed in Area D (new area/home for the backup generator)

     
  Brick work is completed on Area D
     
  ARJO has installed the uni-strutt for the patient lifts in the new patient wing
     
  Roof installation on the west side of the new patient wing
     
  May 26

Running the utilities out to the patient wing and these are electrical conduits

     
  Masons installing the limestone on the patient wing
     
June, 2010    
  June 2

Workers raise an air handler in the process of installing it in the penthouse on the roof of the new patient wing.

     
  June 3

A mock wall was built to demonstrate the brick and limestone finishes on the outside of the new patient wing.
 

     
  June 10

Ambulance drive out of the Garage widened

 

     
  Installing the curtain wall on the north end of the patient wing
     
  Good progress on the underground utilities out to the patient wing
     


  June 16

The fire proofing is being done on the west side of the patient wing

     
  The south curtain wall is being installed
     
  The sheet rockers are topping out. This is when they put the very top piece of sheetrock on so they can fire seal fire rated walls
     
  June 18

Framing the patient rooms

     
July, 2010    
  July 1

Starting to put in ducting

     
  Ducting
     
  Continuing the stud framing in the patient wing
     
  July 16

More of the walls keep going up

     
  The clearstory windows are going in
     
  Mechanical piping and ducting are being installed
     
  July 26

The new generator has been moved into its new brick home, which is on the northeast corner of the current hospital building near the Materials Management dock.

     
August, 2010    
  August 4

Updates in the new patient wing include patient room head walls which must be installed early in the room finishing phase.

     
  August 10

The windows are installed in the new patient wing.

     
  The south end of the patient wing is glassed in. This area will connect to the outside with a Healing Garden.
     
  The north end of the patient wing is glassed in. Brazilian hardwood finishes off the curtain walls.
     
  August 13

Ducting being installed in the ceiling.

     
  Preparing for the temporary connector hallway floor.
     
  New electrical panels being installed.
     
  August 16

Pouring the floor to the hallway.

     
  August 23

Workers install steel framing forming a temporary connector hallway between the new patient wing and the emergency room/surgery area. Once the patient wing is complete in mid-December, which completes Phase 1 of the project, the three former patient pods will be torn down. This will necessitate the need for the hallway to connect the new wing with the rest of the hospital building.

     
" "    

Copyright © 2001 Community Hospital